Hacker News new | past | comments | ask | show | jobs | submit login

My understanding is that it's the latter. "in SCED" basically means they have pre-planned availability that is cheap.

The "Physical Response Capacity" in that graph is the amount of capacity actually available, but it's not part of SCED. However it doesn't say anything about the timeframe it would be available in. Given that ERCOT didn't call for conservation, I would have to assume it was capacity that was "quickly available, but not cheap" rather than "not quickly available", but I don't know for sure.




Being in SCED just means that the resource bid into the real time energy market (which clears every 5 mins), it does not necessarily mean that the resource is cheap to dispatch. The confusion here might be caused by the differences of the ancillary market (PRC) and the energy market (SCED).

Your second paragraph may be answered by this: https://www.ercot.com/gridmktinfo/dashboards/gridconditions. PRC units are available in real time, immediately on request.




Consider applying for YC's Spring batch! Applications are open till Feb 11.

Guidelines | FAQ | Lists | API | Security | Legal | Apply to YC | Contact

Search: